GOK and Development Partners Funded Projects Implemented

GoK FUNDED PROJECTS IMPLEMENTED

The project aims to bring electricity closer to communities by expanding the power network in rural areas. This involves the installation and/or maximization of transformers and supplying power by connecting the target facility/customer to the national grid. Through connecting public facilities such as schools, health centres, markets, and other essential services, nearby households are also able to access electricity.

This helps improve education, healthcare, and local economic activities.

  • A total of 4,006 projects have been implemented across all regions
  • With a combined investment of KSh 35.61 billion
  • Targeting approximately 324,387 customers
  • Reporting period: FY2022/23 – 2025/26
  • REREC Projects Table
    REREC REGIONS PROJECT COST (KSH.) PROJECT COUNT TARGET CUSTOMERS
    CENTRAL EASTERN 3,742,193,437.08 516 26,437
    CENTRAL RIFT 7,125,102,296.88 759 67,520
    COAST 2,213,880,385.17 204 23,972
    MT. KENYA 3,111,915,227.77 356 28,430
    NAIROBI/ NORTH EASTERN 4,242,261,344.16 363 20,612
    NORTH RIFT 5,376,583,329.80 537 51,475
    SOUTH NYANZA 3,114,483,206.34 395 37,033
    UPPER EASTERN 2,291,595,772.99 250 22,929
    WEST KENYA 4,389,951,477.92 626 45,979
    Grand Total 35,607,966,478.11 4,006 324,387

BADEA AND OFID FUNDED PROJECTS IMPLEMENTED BY REREC

-Electrification of Public Facilities-

With support from international development partners, this programme is helping extend electricity to underserved areas across the country. It focuses on connecting key public facilities such as schools, health centres, and markets, while also enabling thousands of nearby households to benefit from reliable power. This contributes to better services and improved livelihoods for communities.
  • A total of 366 projects have been implemented across all regions
  • With a combined investment of KSh 5.77 billion
  • Targeting approximately 28,543 customers
  • REREC Projects Table
    REREC REGIONS PROJECT COST (KSH.) PROJECT COUNT TARGET CUSTOMERS
    CENTRAL EASTERN 1,148,851,188.49 70 5,369
    CENTRAL RIFT 1,100,180,333.39 62 3,370
    COAST 501,940,843.40 28 3,258
    MT. KENYA 224,457,060.80 24 902
    NAIROBI/ NORTH EASTERN 771,875,747.09 26 1,786
    NORTH RIFT 1,043,010,115.77 61 5,823
    SOUTH NYANZA 199,679,223.41 22 2,556
    UPPER EASTERN 164,097,570.75 20 889
    WEST KENYA 613,800,370.92 53 4,590
    Grand Total 5,767,892,454.02 366 28,543